2023 · lead sre · process · disaster recovery game days

DR drills on the calendar, not after the outage

As DR lead, the plan is only as good as the last time it was run. Putting drills on the calendar, and tracking every finding to closure, kept it honest.

1 min readby Rajesh Dhar

The problem

DR plans tend to be written once, reviewed once a year, and tested for real during an outage. By then the system has changed, and the plan describes something that no longer exists.

How I measured it

# when was each application last drilled? (drills.csv: app,last_drill_date,result)
awk -F, -v cutoff="$(date -u -d '-180 days' +%F)" 'NR>1 && $2<cutoff {print $1, $2}' drills.csv

# open findings from past drills, oldest first (findings.csv: id,app,opened,status)
awk -F, 'NR>1 && $4!="closed" {print $3, $2, $1}' findings.csv | sort

Why it kept happening

A drill is never urgent. There's always something more pressing, until the day it's the most pressing thing there is.

The process change

  • A calendar: every application has a drill slot on the calendar, at least twice a year for the critical ones. Booked months ahead, so it's planned work.
  • A script: each drill follows the runbook exactly as written. If someone has to improvise, that's a finding.
  • A real end-to-end test: after failover, a real request through the whole path. A green health check doesn't count.
  • Findings with owners: every gap gets a ticket, an owner and a date, and the next drill checks it's fixed.

What I learnt

The findings were the point. A drill that found nothing was usually a drill that didn't test enough. And improvising during a drill told us exactly where the runbook was wrong.

What I do now

  • Book drills months ahead, like any other planned work.
  • Follow the runbook word for word. Every improvisation is a finding.
  • Track findings to closure and check them in the next drill.

stage 1 looks at when your DR plan was last run → see the engagements